Testing Enclosures : Sealing Rooms for Clean Agents
This bulletin has been prepared to assist anyone who must seal a room for a Clean Agent
system. Obviously, if a Clean Agent concentration test is to be run, the room will need to
be tight to pass that test. Even so, if no concentration test is required, the room will still
need to be sealed. It is the nature of Clean Agent that it will suppress all flame and fire
spread but it cannot in every instance extinguish the initial source of ignition (for instance,
severe electrical short circuit). Therefore it is critical that the Clean Agent remain in the
protected area until emergency personnel have a chance to deal with a possible continuing
source of ignition.
- ALL DOORS leading from the Clean Agent protected areas or into another Clean Agent
zone shall have drop seals on the bottoms, weather stripping around the jams,
latching mechanisms and door closer hardware. In addition, double doors shall have a
weather stripped astragal to prevent leakage between doors and a coordinator to
assure proper sequence of closure. In general, doors shall be treated as though they
are being weatherproofed for outside use with the least amount of light possible
passing around all sides. Doors, which for any reason cannot be kept normally closed,
should be equipped with electromagnets designed to release on alarm. - ALL DUCT WORK leading from or into a protected area may be permanently sealed
off, air tight, with metal plates caulked and screwed in place. Ductwork left in
service from the building air handling unit must have butterfly blade type dampers
installed with neoprene seals. Dampers must be spring loaded or motor operated to
provide 100% air shut-off. It is further recommended that the building air handling
units be shut down to prevent the spread of smoke or Clean Agent into other areas of
the building. - SELF-CONTAINED AIR HANDLING UNITS within the protected zone may be left in
service at the owner's option. However, one must consider the possibility that the air
handling unit could be the source of the fire. Systems not manned 24 hours a day
should be tied-in to shutdown. - PROTECTED AREAS should be enclosed with wall partitions which extend slab-to-slab.
In areas where this is not possible, the ceiling tiles should be clipped. If the ceiling
rests on top of the walls, all tiles should be clipped and a caulk be applied around the
entire perimeter where tile touched the walls. In either case, all tiles should be
clipped in place within 4 feet of any discharge nozzle. - ANY HOLES, CRACKS, OR PENETRATION leading into or out of the protected area must
be sealed. This includes pipe chases and wire troughs.
All walls should be caulked around the inside perimeter of the room where the walls
rest on the floor slab and where the walls intersect with the ceiling slab above. - IF A RAISED FLOOR continues out of the Clean Agent protected area into adjoining
rooms, bulkheads must be installed under the floor, directly under above-floor border
partitions. These bulkheads must be caulked top and bottom.
If the adjoining rooms share the same under-floor air handlers, then the bulkheads
must have dampers installed the same as required for ductwork. See Item #2. - ALL FLOOR DRAINS should have traps and the traps should be designed to have water
in them at all times. - POROUS BLOCK WALLS must be sealed slab-to-slab to prevent gas from passing
through the block. Two or three coats of paint are normally required. Unpainted
block walls are totally unacceptable. - IN GENERAL, the basic intent is to make Clean Agent protected areas as air tight as
possible during and after Clean Agent discharge. Clean Agent is heavier than air and
therefore, openings below floors are usually more critical than those above a ceiling.
However, during discharge the room does get pressurized to some extent and any gas
that can be pushed out of the room will not return. Smaller rooms are much harder
to seal then large rooms because each little crack becomes much more significant as
the surface area to volume ratio changes. - ONCE THE GAS IS DISCHARGED, in most jurisdictions, it must remain in the room at
it’s designed concentration at least ten minutes. The length of time the agent will
remain is directly proportional to the “air tightness” of the room..
The above 10 points are not all inclusive nor guarantee that the concentration test will pass.
They are, however, presented as the most common items which affect Clean Agent
concentration tests. If, in addition to presenting a few specific areas of concern, they
provoke thought about the overall "air tightness" of the enclosure, then they will have served
a good purpose.
Specialized air sealing materials
Hire contractors who are familiar with airsealing, not unspecialized contractors.
| Airseal Manufacturer | Contact | Phone |
| 3M for spray seal | www.3M.com | |
| W.R.Grace for spray seal | www.Grace.com | (800)334-8796 |
| GE Silicones | Customer Development | (800)255-8886 |
| O-Z/Gedney | Patsy Sanders | (918)627-5530 |
| Tremco | Frank Calabrese | (206)252-3372 |
| Thermal Ceramics Inc | (404)796-4280 | |
| 3M | Todd Regenold | (415)563-5992 |
| Flame Stop Inc | James Bower | (817)431-3747 |
| True North Technologies | (416)744-2233 | |
| Unifrax Inc/Carborundum Fibers Division | Sarah Brewer | (716)278-2203 |
| International Protective Coatings Corp | (800)334-8796 | |
| Dow Corning Corporation | (517)496-4000 | |
| Specified Technologies Inc | (800)992-1180 | |
| Thermafiber | (800)426-8127 | |
